Satya Nadella Explains Why Microsoft Cancelled Data Centre Projects in US and Europe

“We continue to expand our datacenter capacity. This quarter alone, we opened DCs in 10 countries across four continents,” Nadella said.

Satya Nadella Explains Why Microsoft Cancelled Data Centre Projects in US and Europe

Key takeaways

  • Microsoft cancels US and Europe data center projects due to oversupply and changing demand forecasts.
  • Evaluate future workload growth factors before committing to new data center builds and leases.
  • Avoid concentrating data center infrastructure in one location to meet global demand effectively.
  • Decisions on data centers involve long-term planning, taking several years from land acquisition to build-out.
  • Despite project cancellations, Microsoft continues to aggressively invest in expanding global data center capacity.

Takeaways drafted with AI from the article text.

“The key thing for us is to have our builds and leases be positioned for what is the workload growth of the future,” Nadella said. He pointed to the evolving nature of AI workloads, distinguishing between traditional training and emerging patterns like pre-training combined with test-time compute. “There’s Moore’s Law, there’s system software, there’s model architecture changes, there’s the app server efficiency.”

Nadella also cautioned against concentrating too much infrastructure in any one location. “You don’t want to be upside-down on having one big data center in one region, when you have a global demand footprint,” he said.

Similarly, Microsoft CFO Amy Hood said that these are long-term decisions. “Just a reminder, these are decisions with long lead times, from land acquisition to build-out, it can take five to seven years, or two to three years," Hood said. “So we're constantly in a balancing act as we monitor demand curves.”

Despite scaling back some leasing activity, Microsoft continues to invest aggressively in its infrastructure. “We continue to expand our datacenter capacity. This quarter alone, we opened DCs in 10 countries across four continents,” Nadella said. 

Microsoft also plans to expand its data centre capacity in Europe by 40 per cent over the next two years.

Microsoft has committed $80 billion in fiscal year 2025 (ending June 2025) on AI-enabled data centres to support AI model training, deployment, and cloud services.

The update came alongside Microsoft’s earnings for the quarter ended March 31, 2025, in which it reported $70.1 billion in revenue, up 13% year-over-year (15% in constant currency). Net income rose 18% to $25.8 billion, with operating income up 16% to $32.0 billion. 

Revenue from the Intelligent Cloud segment was $26.8 billion, a 21% increase. This included a 22% rise in server products and cloud services revenue, led by a 33% growth in Azure and other cloud services.

“In Azure, we expect Q4 revenue growth to be between 34% and 35% in constant currency driven by strong demand for our portfolio of services,” said Hood. “In our AI services, while we continue to bring datacenter capacity online as planned, demand is growing a bit faster. Therefore, we now expect to have some AI capacity constraints beyond June.”

The company attributed its strong performance to growth in cloud and AI offerings. “Cloud and AI are the essential inputs for every business to expand output, reduce costs, and accelerate growth,” Nadella said. “From AI infra and platforms to apps, we are innovating across the stack to deliver for our customers.”

Microsoft Cloud revenue reached $42.4 billion, up 20%. Nadella also shared that more than 15 million people are now using GitHub Copilot, four times as many as last year.

Published

Corrections: AIM corrects errors of fact and notes the change on the story. Spotted one? Tell the editors. Read our editorial standards.

More in this story

Microsoft · 5 stories
  1. AI, New Tech To Contribute $154 Billion To India's GDP By 2021, Says Microsoft India President
  2. AI To Increase Rate Of Innovation In India By 230% In Two Years: Study
  3. You are here: Satya Nadella Explains Why Microsoft Cancelled Data Centre Projects in US and Europe
  4. Former GitHub CEO Raises $60 Mn to Rebuild Software Development for the AI Agent Era
  5. Microsoft’s New TypeScript 7 Promises 8–12x Faster Builds With Native Go Compiler
About the author

Tech Journalist

Siddharth is a media graduate who loves to explore tech through journalism and putting forward ideas worth pondering about in the era of artificial intelligence.

All stories
Belamy · Daily

The day’s AI news, before your first meeting.